Town Works  Current
project budget 
Estimated timeframe
for completion 
Project Manager 
 Edenhope  Water security  $1.2 million November 2011  Chay Tokekar
 Nhill  Upgrade to drinking quality water  $12.6 million  June 2013  Graeme Dick
 Jeparit  Upgrade to drinking quality water  $2.7 million  May 2014  Suresh Unni
 Willaura  Reuse scheme  $0.9 million  June 2011  David McMaster
 Warracknabeal  Waterwater treatment plant upgrade  $3.0 million  May 2012  Eddy Mofardin
 Stawell  Wastewater treatment plant upgrade  $1.5 million  September 2011  Eddy Mofardin
 St Arnaud  Wastewater treatment plant upgrade  $3.0 million  May 2012  Eddy Mofardin
 Rupanyup  New town sewerage schemes  $1.8 million  July 2013  Gary Harper
 Lake Bolac  New town sewerage schemes  $2.9 million  December 2011  Graeme Dick
 Great Western  New town sewerage schemes  $1.4 million  June 2013  Andrew Wundke
 Lake Fyans  Dam safety works  $1.3 million  May 2013  Gary Harper
 Lake Lonsdale  Dam safety works  $3.1 million  June 2013  Gary Harper
 Various  Water main replacements  $4.7 million  June 2013  Chris Baker
 Various  Sewer main replacements  $1.6 million    Roland Heatley
 Various  Water treatment plant upgrades  $2.5 million  June 2013  
 Various  Channel decommissioning project  $15.8 million   June 2012  Peter Cooper 